From Selection to Installation:
Your Chiller Plant Checklist
Everything a facility manager, project engineer, or procurement team needs to get a chiller plant right — from the very first load calculation to the final commissioning sign-off.
Installing a chiller plant is not the kind of decision you revisit lightly. Get it right and you have two or three decades of reliable, energy-efficient cooling that keeps your process, your people, or your product exactly where it needs to be temperature-wise. Get it wrong and you are looking at undersized equipment that struggles on a hot afternoon, oversized machines running at inefficient part-load all year, or installation shortcuts that show up as expensive breakdowns six months after commissioning. This checklist exists so that neither of those outcomes happens to you.
Understanding What You Actually Need Before You Buy Anything
Most chiller procurement decisions go wrong before a single specification is written, because the person making the purchase has not clearly defined what the chiller is supposed to do. This sounds obvious, but in practice it happens constantly — a purchase order gets raised based on a rough floor area estimate, or someone copies the spec from a previous project at a different site, and the resulting system is either undersized or so oversized it spends its entire working life running at 30% load, burning far more electricity than it should.
So before you look at any equipment, answer these questions with precision:
What exactly are you cooling?
Process cooling for manufacturing, HVAC for a building, cold storage for food, chilled water for a data centre, or a pharmaceutical cleanroom each have radically different temperature, flow, and reliability requirements.
When does the load run?
A chiller serving an office building runs daytime hours. A process chiller in a 24/7 manufacturing plant never stops. The operating profile determines energy costs, maintenance scheduling, and whether redundancy is essential.
What inlet and outlet temperatures?
Standard HVAC chilled water runs at 7°C supply, 12°C return. Process cooling may need 15°C, 20°C, or in some cases sub-zero. Every degree lower means significantly higher energy consumption — do not over-specify temperature if you don't need to.
Is the load constant or variable?
A building's cooling load peaks on summer afternoons and drops to near zero at night. A plastic injection moulding process has a near-constant load during production. Understanding load variability determines whether variable speed drives are worthwhile.
What does the site allow?
Available footprint, ceiling height, structural floor load rating, access for maintenance, proximity to noise-sensitive areas, and available electrical supply all constrain which chiller configurations are physically possible at your site.
Will demand grow in 5–10 years?
A chiller plant designed only for today's load that has no room for future expansion forces a costly and disruptive retrofit. Designing in a second chiller connection point costs relatively little upfront and saves enormously later.
The answers to these questions form the brief that every subsequent decision flows from. Without them, you are making expensive guesses with someone else's equipment budget.
Cooling Load Calculation — Getting the Numbers Right
The cooling load calculation is the single most important technical step in the entire chiller selection process. It determines the capacity of the chiller you need, measured in tonnes of refrigeration (TR) or kilowatts (kW). An undersized chiller will never keep up with demand. An oversized one will short-cycle, wear out faster, consume disproportionate energy at part-load, and cost significantly more to purchase than necessary.
There is a common temptation to apply a simple rule of thumb — "one tonne per X square metres of floor area" — and call it done. In light, uniform office spaces with standard glazing, this approach produces a roughly adequate number. In a factory with significant process heat loads, a data centre with dense server racks, a kitchen with cooking equipment, or a building with unusual solar exposure, rule-of-thumb numbers can be off by 30, 40, or even 50 percent. The only right way to calculate cooling load is through a proper heat gain analysis that accounts for every heat source in the space.
What Goes Into a Proper Load Calculation
A thorough cooling load calculation for a building or facility accounts for the following heat gain components. Each one matters, and each one requires actual data from your specific site rather than generic assumptions:
Solar heat gain through glazing and walls — varies enormously by orientation, glass type, and shading. A west-facing glass facade on a factory in Rajasthan generates a very different solar load from the same facade in a shaded industrial park in a cooler climate.
Transmission heat gain through the building envelope — walls, roof, floor, and windows. Insulation quality, wall construction, and roof type all affect this number significantly.
Ventilation and infiltration loads — the heat brought in by outside air through the ventilation system and through gaps in the building envelope. In humid climates, the latent (moisture) component of this load can be as large as the sensible (temperature) component.
Internal heat gains — people generate heat (roughly 70–100W each at rest, significantly more if working physically), lighting generates heat, and equipment generates heat. In an office building, IT equipment is typically the dominant internal heat source. In a factory, process machinery may dwarf everything else combined.
Process loads — if the chiller is serving a process rather than or in addition to a building, the heat generated by the process itself must be precisely measured or calculated from equipment manufacturer data rather than estimated.
Critical Note on Diversity and Safety Factors: Not all loads peak at the same time. A building's solar load peaks in the afternoon while occupancy load peaks at midday. A proper load calculation accounts for this diversity and calculates the coincident peak — the maximum load that actually occurs simultaneously. Adding a blanket 20% safety factor on top of an already-overestimated coincident peak produces chillers that are 40–60% oversized. Apply safety factors judiciously and document what they cover.
For any installation above 20 TR, a proper load calculation should be performed by a qualified HVAC engineer using recognised calculation methodology such as ASHRAE's Heat Balance Method or the Cooling Load Temperature Difference (CLTD) method. The cost of this engineering is trivial relative to the cost of a wrongly sized chiller plant.
Air-Cooled vs. Water-Cooled: The Real Decision
Once you know your cooling load, the next major decision is how the chiller will reject its heat — through air or through water. This choice has substantial implications for capital cost, operating cost, space requirements, maintenance complexity, and environmental impact. It is not simply a technical preference — it is a strategic decision that should be made with full awareness of the trade-offs.
| Factor | Air-Cooled Chiller | Water-Cooled Chiller |
|---|---|---|
| Capital Cost | Lower (no cooling tower needed) | Higher (chiller + cooling tower + condenser pump) |
| Energy Efficiency (COP) | Lower (2.5–3.5 typical) | Higher (4.5–6.5 typical) |
| Footprint | Requires outdoor space for condenser fans | Requires indoor space + cooling tower on roof or outdoors |
| Water Consumption | None (air-cooled) | Moderate (evaporation + blowdown losses) |
| Maintenance Complexity | Lower (no cooling tower, no condenser water treatment) | Higher (cooling tower, condenser water chemistry, Legionella management) |
| Noise Level | Higher (large condenser fans) | Lower (fan noise contained in cooling tower) |
| Best Suited For | Smaller installations, sites without water availability, retrofit projects | Larger installations where energy efficiency payback justifies higher capex |
| Typical Capacity Range | 5 TR to 500 TR | 50 TR to several thousand TR |
The general guidance from an energy efficiency perspective is that for installations above 100–150 TR where the chiller will operate for many hours annually, the higher capital cost of a water-cooled system is typically recovered through energy savings within 3–5 years. Below that threshold, or for installations with limited annual operating hours, the simpler air-cooled configuration often makes more practical sense.
Water availability and quality is an important additional consideration. If your site is in a water-scarce region or has very high TDS source water, the operating cost and complexity of managing a cooling tower water circuit can shift the economics significantly in favour of air-cooled equipment — even at larger capacities.
The right chiller type is not the one with the best energy rating in the catalogue. It is the one that performs best in your specific climate, with your specific load profile, on your specific site — for the entire life of the asset.
Chiller Types and When to Use Each
Within the air-cooled and water-cooled categories, there are further choices to make based on the compressor technology. Each compressor type has different efficiency characteristics, capacity ranges, part-load performance, and maintenance profiles. Understanding the basics helps you ask the right questions when evaluating supplier proposals.
Screw Chillers
Screw chillers use twin helical rotors to compress refrigerant. They are the workhorses of the industrial and commercial chiller market — robust, relatively simple, available from 30 TR to 500+ TR, and competitively priced. Modern screw chillers with variable speed drives have excellent part-load efficiency. They are the default choice for most medium to large industrial process cooling applications and are well-suited to the 24/7 operating profiles common in manufacturing. Maintenance is moderate and well-understood — screw elements require periodic oil analysis and occasional bearing replacement.
Centrifugal Chillers
Centrifugal chillers use a high-speed impeller to accelerate refrigerant vapour, converting velocity to pressure. They are the most energy-efficient option at or near full load in large capacities — typically above 200 TR — and are the standard choice for large commercial buildings, district cooling plants, and major industrial facilities. Their efficiency advantage is greatest at full load; at part load, efficiency drops more steeply than screw chillers unless magnetic bearing technology or variable speed drives are incorporated. Centrifugal chillers have fewer wearing parts than reciprocating or screw machines and can have very long service lives when properly maintained.
Scroll Chillers
Scroll chillers use two spiral-shaped scrolls to compress refrigerant. They are quiet, vibration-free, and simple — but limited to smaller capacities, typically below 60 TR. Scroll chillers are widely used in commercial buildings, small process applications, and modular chiller configurations where multiple small units are combined to achieve larger capacity with redundancy. They have fewer moving parts than screw or reciprocating machines and are generally lower maintenance.
Absorption Chillers
Absorption chillers use heat rather than electricity as their primary energy input — typically waste heat from a process, steam, or hot water. They are the right choice when significant waste heat is available (above 80–90°C), electricity is expensive or scarce, or a facility wants to improve overall energy utilisation through combined heat and power (CHP) integration. Absorption machines have no compressor, move very few mechanical parts, and can be remarkably reliable — but they require more careful water chemistry management and are significantly larger per tonne of cooling than vapour compression chillers.
The Pre-Purchase Checklist
Before committing to a purchase order, work through this checklist systematically. Each item represents a decision point where inadequate attention creates problems that are far more expensive to fix after the equipment arrives than before.
Not a rule of thumb, not an estimate — a documented calculation by a qualified engineer that accounts for all heat sources, diversity, and future load growth.
Confirm the exact temperature difference (delta-T) required. A 5°C delta-T (7°C supply, 12°C return) is standard HVAC; process applications often differ. The chiller must be rated at your actual operating temperatures, not catalogue standard conditions.
A chiller's published capacity is typically at standard test conditions (e.g., 35°C ambient for air-cooled). Your site may hit 44°C in summer. Ensure the selected chiller's rated capacity at your maximum design ambient still meets your load — not just at standard conditions.
Most chillers spend 90%+ of their operating life below full load. A chiller with exceptional full-load efficiency but poor part-load efficiency can consume more energy annually than a cheaper machine with better IPLV. Ask for IPLV or NPLV data, not just peak COP.
Refrigerant regulations continue to tighten globally. Chillers using HFCs with high global warming potential (GWP) face increasing restrictions. Evaluate options using low-GWP refrigerants (R-32, R-1234ze, R-513A) to ensure regulatory compliance over the asset's lifetime.
Large chillers are extremely heavy — a 200 TR water-cooled screw chiller can weigh 4,000–6,000 kg. Confirm with a structural engineer that your floor can support the static and dynamic loads before specifying equipment location.
Check that your electrical infrastructure can support the chiller's full-load amperage plus the associated pumps, cooling tower fans, and controls. Many sites discover only at this stage that a transformer upgrade is required — add months and significant cost to the project timeline.
Can the chiller physically get from the delivery vehicle to its installed location? Check door widths, ceiling heights, elevator capacity (if applicable), and crane access points. Planning this after the equipment arrives is a crisis; planning it before is a checklist item.
Is a single chiller acceptable, or does the application require N+1 redundancy (one standby)? Process applications where downtime has direct production cost typically require at least partial redundancy. Decide this before equipment is specified, not after.
A chiller from a supplier with no service infrastructure in your region is a significant operational risk. Confirm local service engineer availability, critical spare parts stock, and the realistic response time for emergency callouts before signing the purchase order.
Site Preparation Checklist
A chiller that arrives at a site that is not ready for it is an extremely expensive problem. Equipment sitting on a construction site waiting for civil work to complete ties up capital, risks damage, and delays production. Work through site preparation in parallel with equipment procurement so the two converge at the same time.
The chiller must sit on a properly designed reinforced concrete inertia pad. The pad dimensions, thickness, and reinforcement specification come from the chiller manufacturer's foundation drawing. Using a generic slab or an existing unprepared floor is a vibration and structural risk.
Chillers generate vibration during operation. Anti-vibration mounts prevent this vibration from transmitting through the structure to adjacent spaces. The correct mount type and stiffness must be matched to the chiller's weight and operating frequency — do not substitute generic rubber pads.
Chilled water flow and return headers, condenser water headers (for water-cooled), expansion vessel connections, and drain points should all be installed and pressure tested before the chiller arrives. Do not leave this work to be done around installed equipment.
The main electrical isolator, overload protection, and power distribution board for the chiller plant should be installed, inspected, and certified before equipment commissioning begins. Power should be available and verified at the correct voltage and phase.
For water-cooled systems, the cooling tower, its basin, the condenser water pump set, and the associated pipework should all be installed before chiller commissioning. The complete condenser water circuit should be flushed and chemically cleaned before it is connected to the chiller condenser.
Chillers require clear access for tube bundle removal (both evaporator and condenser), oil sampling, refrigerant charging ports, and control panel access. Check the manufacturer's minimum clearance requirements and mark them on the floor plan before installation is complete.
The chilled water circuit requires a make-up water connection for system fill and pressure top-up. A suitable drain point is needed for system flushing and maintenance. Both must be in place before fill and pressure testing of the system.
If the chiller plant is to be monitored and controlled through a building management system or SCADA platform, communication cables, control panels, and integration hardware should be installed before commissioning so that the chiller's BACnet, Modbus, or proprietary communications can be tested during start-up.
Installation Checklist
The installation phase is where specification decisions meet physical reality. Experienced installation teams will follow manufacturer guidelines closely — but as the facility owner or project manager, you should know what to look for and what questions to ask. A poorly executed installation can compromise a well-specified chiller for its entire working life.
The chiller must be precisely levelled after placement. Most manufacturers specify maximum permissible tilt angles — typically less than 3mm per metre. Improper levelling affects oil return in the refrigeration circuit and can cause operational problems and premature wear.
Rigid pipe connections that transmit vibration directly into the building structure and back into the chiller create noise complaints and accelerate wear on chiller nozzle connections. Flexible bellows or rubber connections should be fitted at all chiller pipe connection points — evaporator, condenser, and any drain connections.
New pipework invariably contains flux residue, pipe scale, welding debris, and construction contamination. This material must be flushed from the system before the chiller is connected. Allowing a new chiller to circulate debris-laden water through its evaporator and condenser tubes will cause damage within weeks that voids the warranty.
Y-type or basket strainers should be installed on the evaporator inlet and condenser inlet (for water-cooled machines). These are the last line of defence against debris reaching the chiller's tube bundle. Strainer mesh size should match the manufacturer's recommendation — typically 1mm or finer.
A chiller must not start unless adequate water flow is confirmed through both the evaporator and condenser circuits. Flow switches provide this protection. They must be correctly positioned in straight pipe runs (as specified by the switch manufacturer) and wired into the chiller's safety interlock circuit.
Pressure and temperature test points should be fitted at inlet and outlet of each water circuit — evaporator and condenser. These points are essential for performance monitoring, fault diagnosis, and annual efficiency checking. Fitting them during installation costs almost nothing; retrofitting them later requires system shutdown.
Chilled water pipework — both flow and return — must be insulated to prevent condensation and heat gain. Insulation is dramatically easier to install on dry pipe than on a pipe already filled with cold water and running with condensation. Complete all insulation before filling the system.
The complete chilled water and condenser water circuits should be hydraulically pressure tested before the chiller is connected and before any pipe insulation is applied over joints. Test pressure is typically 1.5× the system design pressure. All flanged joints, valved connections, and welded points should be checked for leaks.
The chiller's electrical installation — power supply, control wiring, earthing, and overload protection — must be inspected and certified by a licensed electrical contractor before the manufacturer's commissioning engineer operates the machine. Running equipment on uncertified electrical installation is both an insurance and a safety risk.
Commissioning Checklist
Commissioning is the process of verifying that the installed system actually performs as specified. It is not the same as start-up. Start-up means the machine switches on. Commissioning means the machine switches on, operates safely, meets its specified capacity and efficiency, and all controls, safeties, and integrations function correctly. Commissioning should always be carried out by the chiller manufacturer's trained engineer, not by the installation contractor acting alone.
Pre-Start Verification
Before the chiller is powered up, the commissioning engineer verifies oil level, refrigerant charge, crankcase heater operation (heaters must be on for at least 24 hours before initial start on most screw and centrifugal chillers), and all field wiring connections. Flow through both water circuits must be confirmed and measured — not assumed.
Allow: 4–8 hoursControls and Safety Interlock Testing
Every safety interlock must be tested in isolation before the chiller is started under load. This includes high-pressure and low-pressure cutouts, evaporator freeze protection, flow switch operation, motor overload protection, and any external interlocks (building management commands, fire system, etc.). A safety that has never been tested is not a safety — it is a label.
Allow: 2–4 hoursInitial Start and Unloaded Run
The first start is typically done at minimum load — either using an unloading valve or by reducing water flow temporarily. The commissioning engineer monitors refrigerant pressures, temperatures, vibration, oil pressure, and motor amperage during the initial run period. Any anomaly found at this stage is orders of magnitude cheaper to address than one found six months into full operation.
Allow: 2–4 hoursFull-Load Performance Test
With the system running at as close to full design load as possible, all operating parameters are recorded and compared against the specified design conditions. Chilled water supply and return temperatures, condenser water temperatures, refrigerant suction and discharge pressures, compressor motor amperage, and system COP are all measured and documented. This record becomes the baseline against which future annual performance checks are compared.
Allow: 4–8 hoursOperator Training and Handover
The commissioning engineer should conduct structured training for the facility's operators covering: routine start-up and shutdown procedure, normal operating parameter ranges and alarm responses, log sheet completion, basic fault identification, and the maintenance schedule. A chiller is only as reliable as the people operating it. This session should be documented and signed off by both the engineer and the operators.
Allow: 3–4 hoursCommissioning Documentation Handover
At handover, the facility should receive: commissioning report with all recorded operating parameters, as-built drawings for the chiller plant, operation and maintenance manuals, spare parts list with recommended initial stock, warranty certificate, and contact details for the manufacturer's service department. These documents are not optional extras — they are part of what you paid for.
At handoverNever accept a verbal commissioning sign-off. Insist on a written commissioning report signed by the manufacturer's engineer that records all measured operating parameters against design values. This document is your evidence of the chiller's condition at handover and is essential for any future warranty claims.
Water Treatment — The Step Most Chiller Owners Skip
This is where many technically sound chiller installations go quietly wrong over the years following commissioning. Chiller tube bundles — both evaporator and condenser — are precision heat exchangers. Their efficiency depends entirely on clean metal surfaces for heat transfer. Scaling, corrosion, biological fouling, and suspended solids all degrade this heat transfer, and the efficiency loss is insidious: it happens gradually, invisibly, and is often not noticed until the chiller is struggling to maintain setpoint on a moderately warm day or electricity bills have crept up noticeably.
For water-cooled chillers, the cooling tower water circuit is particularly critical. Open cooling towers are exposed to the atmosphere and continuously concentrate dissolved minerals through evaporation while also collecting airborne dust, pollen, and biological matter. Without active water treatment, the condenser water in a cooling tower circuit will scale, corrode, and — most seriously — support the growth of Legionella bacteria, a health hazard with significant legal implications.
Chilled Water Circuit Treatment
The closed chilled water circuit is less problematic than the open condenser water circuit, but it still requires attention. Dissolved oxygen in the system water causes corrosion of steel components — pipework, pump casings, and valve bodies. An appropriate corrosion inhibitor dosed at commissioning and maintained at the correct concentration prevents this. The system should also include a scale inhibitor if the make-up water has significant hardness, and a biocide to prevent biological growth in any stagnant sections of pipework.
The water quality of the make-up supply to the chilled water circuit matters. If your make-up water has high TDS, high hardness, or iron content, consider installing a softener or reverse osmosis system on the make-up line to reduce the dissolved mineral load entering the system. This is a relatively modest investment that significantly extends the service interval between tube bundle cleanings and reduces chemical consumption.
Cooling Tower Water Circuit Treatment
The cooling tower circuit requires active water treatment management, not just an initial chemical dose. The key parameters to monitor and control are: pH (typically maintained between 7.0 and 8.5), conductivity (controlled through blowdown to limit total dissolved solids concentration), calcium hardness (to manage scale risk), Langelier Saturation Index (LSI — the key scale/corrosion balance indicator), and biological counts (to control Legionella and other biological growth).
The financial case for water treatment: A 1mm scale deposit on condenser tube surfaces reduces heat transfer efficiency by approximately 10%. A 3mm deposit can reduce efficiency by 30% or more, forcing the chiller to consume significantly more electricity for the same cooling output. The annual cost of cooling tower water treatment is typically recovered many times over in reduced electricity consumption alone — before accounting for the extended equipment life and avoided tube bundle cleaning costs.
Water Treatment Checklist for Chiller Plants
Know what is in your water before you fill the system. TDS, hardness, pH, alkalinity, iron, chlorides, and microbiological quality all affect which chemical treatment programme is appropriate.
Do not use generic off-the-shelf chemicals without a programme designed for your specific water chemistry and system. A water treatment specialist who has reviewed your source water analysis should recommend specific products, dosing rates, and monitoring frequencies.
Manual chemical dosing is unreliable and labour-intensive. An automatic conductivity-based blowdown controller and chemical dosing pump system maintains water quality within specification continuously without depending on operator memory or availability.
Any cooling tower is a potential Legionella risk. A formal Legionella risk assessment must be completed, a written Scheme of Control documented, and a responsible person designated for ongoing Legionella management. This is not just best practice — it is a legal obligation in most jurisdictions.
If your cooling tower make-up water or local air quality results in high suspended solids in the tower basin, a side-stream filter (typically 10–25% of system flow rate) continuously removes particulates and dramatically reduces biological fouling and tube bundle soiling rates.
Cooling tower water should be tested monthly by an accredited laboratory for full chemical and biological panel, including Legionella. Do not rely solely on on-site test kits for Legionella monitoring — laboratory testing is required for defensible compliance records.
Ongoing Maintenance Checklist
A chiller plant that is commissioned correctly and then neglected will degrade steadily and quietly until an expensive failure makes the neglect impossible to ignore. The maintenance schedule is not bureaucracy — it is the difference between a chiller that delivers 20–25 years of reliable service and one that is struggling at year 8 and replaced at year 12.
Suction and discharge pressures, chilled water and condenser water temperatures, motor amperage, and oil pressure should all be checked monthly and compared against the commissioning baseline record. Creeping deviation is an early warning sign of tube fouling, refrigerant issues, or mechanical wear.
Strainer elements accumulate debris over time and, if not cleaned, restrict flow and reduce chiller efficiency. Monthly inspection and cleaning takes minutes and prevents the far more disruptive problem of reduced evaporator or condenser flow triggering chiller trips.
Refrigerant loss through minor leaks is common over a chiller's life. A low refrigerant charge reduces capacity and efficiency and, in severe cases, can damage the compressor. Monthly visual inspection of connections and an annual leak check with electronic detectors is the appropriate monitoring interval for most applications.
Review the previous month's laboratory water test results and adjust chemical dosing if any parameters are outside the target range. Record all adjustments made.
An oil sample sent to a laboratory for analysis reveals compressor wear through metal particle content (ferrous debris indicates bearing wear), moisture ingress, acid formation, and viscosity degradation. This is the most cost-effective predictive maintenance tool available for chillers — a ₹3,000 oil test can identify a developing compressor problem before it becomes a ₹5 lakh failure.
Evaporator and condenser tube bundles should be inspected annually for fouling and, where water-cooled, physically cleaned with tube brushes or high-pressure water. Every 3–5 years, an eddy current test of condenser tube walls detects thinning from corrosion before a tube fails catastrophically and floods the refrigerant circuit with water.
Measure actual operating COP at a known load and ambient condition, and compare against the commissioning baseline and manufacturer's performance curve. A chiller whose COP has dropped 15% from commissioning baseline is absorbing significantly more electricity for the same cooling output — identifying and addressing the cause (typically fouled tubes or low refrigerant) pays back quickly.
Annual physical inspection and cleaning of cooling tower internals — fill media, drift eliminators, basin, distribution heads, and fan blades — combined with a thorough chemical disinfection of the complete condenser water circuit. This annual clean is a mandatory element of most Legionella risk management schemes.
Pressure switches, temperature sensors, flow switches, and motor protection devices should all be calibrated or verified annually. A safety interlock that has drifted out of calibration either fails to trip when it should (allowing equipment damage) or trips spuriously (causing nuisance shutdowns).
A Good Checklist Is Only As Good As Its Execution
Chiller plant projects that go smoothly are not the result of luck — they are the result of methodical preparation, clear specifications, proper installation discipline, and a maintenance culture that treats the checklist as a tool rather than a formality. Every item on every checklist in this guide exists because someone, somewhere, skipped it and paid for that decision with an expensive breakdown, a failed commissioning, or a compliance problem that could have been avoided.
The investment in getting a chiller plant right — from a thorough load calculation through to a proper commissioning test and a structured maintenance programme — is marginal relative to the cost of the equipment itself. But its impact on equipment life, energy cost, operational reliability, and total cost of ownership over 20 years is enormous.
At Kaveri RO, we bring the same systematic, detail-oriented approach to chiller plant projects that we apply across our full range of industrial water and cooling solutions. From helping you work through your initial load calculation and chiller type selection, through to recommending the right water treatment programme for your specific water chemistry and cooling system, our team has the technical depth to support your project at every stage — not just at the point of equipment sale. If you are planning a chiller plant installation or looking to optimise an existing system that is not performing as it should, we would welcome the conversation.
Speak with a Kaveri RO Engineer →